Location: Englewood, CO
Client: Craig Hospital
Mechanical Contractor: Mtech Mechanical
Craig Hospital located in Englewood, CO specializes in spinal cord injuries and traumatic brain injury rehabilitation. The facility consists of 3 buildings: East, Family Housing and the Main Hospital. ATS Rocky Mountain was selected to perform a phased replacement of the legacy Siemens control system at the Hospital’s three buildings. The hospital remained in operation throughout the project, with patients on the premises 24 hours a day.
The controls retrofit began in 2013 and was completed in 2016. For the Main Hospital building ATS replaced all the existing legacy controls utilizing Alerton hardware and Compass Operator Workstation software. For the East and Family Housing buildings ATS utilized Alerton’s BCM-FPCS to replace controls for the RTUs, chillers and boilers while integrating to the existing Siemens zone control. By utilizing the existing zone controls, ATS lowered the installation cost while updating the hospital’s critical controls infrastructure.